PPWR technical documentation is the file that a manufacturer must draw up under Annex VII of the Packaging and Packaging Waste Regulation (Regulation (EU) 2025/40) to show that a packaging type meets Articles 5 to 12, and it has been required before placing packaging on the market since 12 August 2026. No notified body is involved.

The file is the core proof of conformity under the EU Packaging and Packaging Waste Regulation (PPWR) for every packaging type. This page sets out what it contains, which articles it covers, how to build it and who keeps it.

Compiled by the PackagingRegulation.org Editorial Team from the Regulation's text on EUR-Lex and the cited official sources; see our methodology and fact-checking.

Item Value Source
Legal basis Conformity assessment under Module A; file in Annex VII point 2 Art. 15(2), 38, Annex VII PPWR
Procedure Internal production control; no notified body, no CE marking Art. 38, Annex VII PPWR
Drawn up by The manufacturer, before placing on the market Art. 15(2) PPWR
Required since 12 August 2026 (general application) Art. 71 PPWR
Contents Elements (a) to (f) of point 2 and a risk analysis Annex VII point 2 PPWR
Retention 5 years (single-use packaging), 10 years (reusable packaging) Art. 15(3) PPWR
On request Within 10 days, in electronic form Art. 15(10) PPWR
Missing Formal non-compliance Art. 62(1)(d) PPWR

What Is Technical Documentation under the PPWR?

The technical documentation is the evidence file that makes it possible to assess whether a packaging type conforms to the PPWR requirements that apply to it, and it must include an adequate analysis and assessment of the risks of non-conformity (Annex VII point 2 PPWR).

It also specifies the applicable requirements and covers design, manufacture and operation as far as relevant.

Art. 15(2) PPWR places the file in a fixed sequence. Before placing packaging on the market, the manufacturer carries out the Art. 38 conformity assessment or has it carried out on its behalf, draws up the Annex VII file, and then draws up the declaration once compliance is demonstrated. "Technical file" and "technical dossier" mean the same document.

Does a notified body have to check the technical documentation?

No: Module A is internal production control, so the manufacturer assesses and declares conformity on its sole responsibility, no notified body is involved and no CE marking is affixed for the PPWR. Recital 109 adds that a CE marking on packaging does not indicate PPWR compliance.

How Does PPWR Conformity Assessment Work under Annex VII Module A?

Conformity assessment is the process demonstrating whether the sustainability, safety, labelling and information requirements of the PPWR relating to packaging have been fulfilled (Art. 3(1)(65) PPWR), and Art. 38 requires it to follow the Module A procedure of Annex VII. Module A ends with the PPWR EU declaration of conformity, explained on its own page.

Annex VII sets out the four working elements of Module A in points 2 to 5:

  • The manufacturer draws up the technical documentation (point 2).
  • The manufacturer ensures that the manufacturing process and its monitoring keep the packaging in line with the file and the requirements (point 3).
  • A written declaration is drawn up for each packaging type and kept with the file (point 4).
  • An authorised representative may keep the file if the mandate says so (point 5).

Under point 1, the manufacturer fulfils points 2 to 4 and ensures and declares, on its sole responsibility, that the packaging meets the applicable Art. 5 to 12 requirements. Module A rests on Decision No 768/2008/EC (recital 108).

Can a laboratory or consultant carry out the conformity assessment?

Yes: Art. 15(2) PPWR lets the manufacturer carry out the conformity assessment or have it carried out on its behalf, and Commission Notice C/2026/3084 (OJ C, 10.6.2026) names a laboratory or a certification scheme as examples.

The manufacturer stays the sole operator bearing legal responsibility, whoever drafted the documents, and drawing up the file cannot be handed to an authorised representative (Art. 17(2), last subparagraph). What laboratories measure for the file is described under PPWR testing.

What Must the Annex VII Technical File Contain?

Annex VII point 2 lists six elements that the technical file must contain wherever applicable, from a general description of the packaging to its test reports. The point opens with the risk analysis and the applicable requirements; the elements are required "at least" wherever they apply.

Point What it holds
Opening Adequate analysis and assessment of the risks of non-conformity; the applicable requirements; design, manufacture and operation as far as relevant
2(a) General description of the packaging and its intended use
2(b) Conceptual design, manufacturing drawings and the materials of the components
2(c) Explanations needed to understand the drawings and the operation of the packaging
2(d) List of standards and specifications applied, see below
2(d)(i) Harmonised standards applied
2(d)(ii) Common specifications applied
2(d)(iii) Other specifications for measurement or calculation
2(d)(iv) The parts of those standards or specifications that were applied
2(d)(v) Solutions adopted to meet the requirements where none of them was applied
2(e) Qualitative description of the assessments under Art. 6, 10 and 11
2(f) Test reports

Point 2(d)(v) matters where no standard exists: the manufacturer then describes the solutions it adopted. Point 2(e) covers only Art. 6, 10 and 11; the other articles reach the file through their own paragraphs.

Which test methods and specifications can the file rely on?

Tests, measurements and calculations for the file must use reliable, accurate and reproducible methods that take into account the generally recognised state of the art and give results of low uncertainty (Art. 35 PPWR). Methods and packaging that conform to harmonised standards whose references are published in the Official Journal are presumed to conform (Art. 36(1) and (3)).

Common specifications give the same presumption (Art. 37(1)). As of 14 November 2026, no harmonised standard reference is published under the PPWR and no common specification is adopted. For minimisation, Directive 94/62/EC Art. 9(1) and (2) keep applying until 31 December 2029 (Art. 70(1)(b)). Progress on PPWR harmonised standards is tracked on its own page.

Which PPWR Requirements Must the Technical Documentation Cover?

The technical documentation must cover every requirement laid down in or pursuant to Articles 5 to 12 that applies to the packaging, and eight articles name the Annex VII file as the place where compliance is demonstrated. Art. 15(1) allows only packaging that conforms to Articles 5 to 12 to be placed on the market.

Requirement Article naming the file What the file shows
Substances of concern, PFAS Art. 5(6) Compliance with the heavy-metal limit of 100 mg/kg (sum) and the PFAS limits of 25 ppb, 250 ppb and 50 ppm (Art. 5(4), 5(5))
Recyclability Art. 6(9) Qualitative description of the assessment (point 2(e))
Recycled content Art. 7(6) Recycled content of plastic packaging, in the format of the Art. 7(8) act
Compostable packaging Art. 9(4) Compliance with the Art. 9 requirements
Minimisation Art. 10(4) Documentation under points (a) to (c), see below
Reusable packaging Art. 11(3) Compliance with the Art. 11 requirements
Environmental claims Art. 14 Proof of the claimed property
Re-use systems Art. 26(2) Description of the system and Annex VI confirmations

For minimisation, the file holds the specifications, standards and conditions measured against Annex IV (Art. 10(4)(a)), the design requirements that prevent further reduction (point (b)) and the tests, studies, modelling or simulations used (point (c)). For reusable packaging, the assessment takes into account in the first place the Art. 11 requirements (Art. 10(4), last subparagraph).

Above 50 mg/kg total fluorine, the REACH manufacturer, importer or downstream user provides fluorine proof on request so that the file can be drawn up (Art. 5(5)(c)). The limits and the test sequence are set out under PPWR PFAS limits for food-contact packaging.

How is recycled content documented before the Article 7(8) implementing act?

Manufacturers or importers demonstrate the recycled content of plastic packaging in the technical information referred to in Annex VII (Art. 7(6) PPWR), but the format is left to an implementing act under Art. 7(8). That act is due by 31 December 2026 and is not adopted as of 14 November 2026.

The recycled content targets start on 1 January 2030 or 3 years after that act, whichever is later (Art. 7(1)). Implementing Decision (EU) 2026/1425 (OJ L, 2026/1425, 3.7.2026) sets the method for single-use plastic beverage bottles under the Single-Use Plastics Directive and is not the Art. 7(8) act.

How are exemptions documented in the technical file?

An exemption that applies directly still has to be shown in the file: Commission Notice C/2026/3084 reads the Art. 7(5) exemptions from the recycled content targets as needing no grant by any authority but substantiation in the technical documentation. The same Notice has a custom design under Art. 29(4)(b) documented in the file.

For minimisation, the Commission's PPWR FAQ (non-binding), section VII, says the evidence belongs in the file and a licensing number is not sufficient. Double walls or false bottoms must be proven necessary by tests in the file. Both documents are non-binding; see PPWR guidance and FAQ.

PPWR Technical Documentation Template: Building the Annex VII File Step by Step

The PPWR gives no fill-in form for technical documentation: the structure comes from Annex VII point 2, and the file must allow an authority to assess conformity. The seven steps below follow the order of Art. 15 and Annex VII for one packaging type.

  1. Confirm the manufacturer and define each packaging type and its identification by type, batch or serial number (Art. 15(5)).
  2. List the Art. 5 to 12 requirements that apply to that type, since only conforming packaging may be placed on the market (Art. 15(1)).
  3. Collect supplier documentation, including fluorine proof where relevant (Art. 16(1), Art. 5(5)(c)).
  4. Describe the packaging, its intended use, design, drawings and materials (point 2(a) to (c)).
  5. Run the assessments and tests, then list the standards or describe the solutions adopted (point 2(d), (f)).
  6. Write the risk analysis and the Art. 6, 10 and 11 descriptions, then draw up the declaration (point 2(e), Art. 39).
  7. Control manufacturing, keep the file for 5 or 10 years and re-assess when conformity could be affected (point 3, Art. 15(3), 15(4)).

Who Draws Up, Keeps and Updates the Technical Documentation?

The manufacturer draws up the technical documentation before the packaging is placed on the market, and it keeps the file for 5 years for single-use packaging and 10 years for reusable packaging (Art. 15(2) and 15(3) PPWR). Suppliers provide their documentation under Art. 16(1). Every other Art. 15 duty is listed under PPWR manufacturer obligations.

Operator Duty Period Article
Manufacturer Draws up and keeps the file; provides it on request 5 or 10 years; within 10 days Art. 15(2), 15(3), 15(10) PPWR
Supplier Provides documentation, including Annex VII parts for Art. 5 to 11 In a language the manufacturer easily understands Art. 16(1) PPWR
Authorised representative (Art. 17) Keeps the file if mandated; never draws it up 5 or 10 years; within 10 days Art. 17(2), Annex VII point 5 PPWR
Importer Checks the assessment and the file; keeps the declaration and has the file available 5 or 10 years; within 10 days Art. 18(2)(a), 18(7), 18(8) PPWR

On a reasoned request from a national authority, the manufacturer makes the file available within 10 days of receipt, in electronic form and on paper on request (Art. 15(10)). Suppliers cannot refuse the documentation, according to the Commission's PPWR FAQ (non-binding), section X.

An authorised representative keeps the file only if the mandate says so, and never draws it up (Art. 17(2), Annex VII point 5).

Roles shift under Art. 21 and Art. 15(12), which moves the duty and does not remove it. Art. 15(11) exempts custom-made transport packaging for configurable medical devices. The importer's other checks are set out in the PPWR obligations of importers.

When must the conformity assessment be repeated?

The manufacturer must re-assess the packaging under Art. 38 when its conformity could be affected, and must take into account changes in packaging design or characteristics and changes in the standards or specifications by reference to which conformity is declared (Art. 15(4) PPWR). Series production must also follow procedures that keep the packaging in conformity.

What Happens If the Technical Documentation Is Missing or Incomplete?

A market surveillance authority that finds the technical documentation not available, not complete or containing errors requires the economic operator to put an end to that formal non-compliance (Art. 62(1)(d) PPWR).

Where the formal non-compliance persists, the Member State takes measures to prohibit making the packaging available or to have it recalled or withdrawn (Art. 62(2)).

The Regulation sets no EU fine amount: Member States notify their penalty rules by 12 February 2027 (Art. 68), as explained under PPWR penalties and market surveillance.

How Does the Technical File Relate to the Declaration and Other Duties?

The technical file is the evidence behind the EU declaration of conformity, which must contain the elements of the Annex VII module and refer to the standards or specifications used (Art. 39(2), Annex VIII point 6 PPWR).

EPR registration is a separate duty in each Member State's register (Art. 44). The file is one step of PPWR compliance.

In which language must the technical documentation be provided?

The PPWR sets no single language for the file itself: on a reasoned request the manufacturer provides it in one or more languages that the requesting authority can easily understand (Art. 15(10) PPWR), and suppliers provide their documentation in a language the manufacturer easily understands (Art. 16(1)).

Can software tools assemble the technical file?

Software can collect supplier data and store the file, but the manufacturer remains solely responsible for its content and the obligation to draw it up cannot be handed to an authorised representative (Art. 17(2) PPWR). What such tools cover is described under PPWR compliance software.

Sources